WHEN THE PANELS COME DOWN

Decommissioning: Who Pays?

Illinois sets the cleanup rules for utility-scale solar, and counties can’t require more. Here’s what the state agreement actually guarantees, and when.

10%

Of cleanup cost guaranteed by year 1
Source: Standard Solar AIMA

50%

By year 6
Source: Standard Solar AIMA

100%

Not until year 11
Source: Standard Solar AIMA

12 months

To finish removal after end of useful life
Source: Standard Solar AIMA

The Rules in Plain English

A plan, filed with the county

The developer files a deconstruction plan with the county during the permit process and updates it by the end of year 10. (AIMA)

OUR CONCERN

Money phased in slowly

Financial assurance (a bond or similar, with the county or landowner as beneficiary) phases in 10% / 50% / 100% at years 1, 6 and 11. (AIMA)

Counties can't ask for more

Counties may not require construction, decommissioning or financial-assurance standards stricter than the standard AIMA. (§5-12020(j))

What must be removed

Panels, racking and piles, foundations to 5 ft, inverters and substations, buildings and access roads (unless the landowner keeps them). Cables 5 ft or deeper may stay. (AIMA)

Salvage value

Salvage can reduce the estimate only if the county agrees the salvage interests are subordinate to the financial assurance. (AIMA)

Abandonment

A project is presumed at end of life if the owner misses landowner payments for 6 consecutive months. If removal isn’t done within 12 months after end of life, it counts as abandoned. (AIMA)

What Would Change

IN COMMITTEE

HB 5477

Would require an engineer’s deconstruction plan and let counties change the level of financial assurance. (Synopsis)

LOCAL ACTION

Grundy County's ordinance

Grundy’s June 2026 ordinance calls for irrevocable financial assurances for decommissioning and reclamation. (Shaw Local)

Cleanup guarantees shouldn't take 11 years.

Tell your legislators to front-load decommissioning protections.